02.04.2026. SIA “Tiesu namu aģentūra” Has Signed Agreements with the Central Finance and Contracting Agency for the Implementation of Three European Union Fund Projects.

  1. No. 2.1.1.4/1/25/I/009, “Improving the Energy Efficiency of the Administrative Building in Sigulda, Šveices iela 27”

Project description.

Improving energy efficiency simultaneously ensures a positive and favorable impact on the environment and ensures quality and appropriate conditions for the staff and clients of the Riga District Court, in the administrative building in Sigulda, Šveices iela 27.

Project objective.

Improving the energy efficiency of the building in Sigulda, Šveices iela 27, by carrying out energy certification of the building and construction works to increase energy efficiency, including implementing smart management solutions and improving infrastructure, in order to achieve primary energy savings for the building and promote progress toward zero-energy buildings.

Planned results.

  1. An energy certificate for the building has been prepared, with a report on economically justified energy-efficiency-improving measures.
  2. A building design has been prepared and approved by the building authority.
  3. Construction works – energy-efficiency-improving measures – have been carried out in accordance with the developed building design (under the supervision of a certified construction supervisor and a certified author’s supervisor).
  4. Primary energy savings relative to the total primary energy consumption before the start of the project – 63%.

Project costs.

The planned total eligible costs of the project – EUR 215 713,35

Sources of financing for the project’s planned eligible costs – 61,71% of eligible costs is planned to be covered by European Regional Development Fund financing (EUR 133 111,07), 10,89% by state budget financing (EUR 23 490,19), and 27,40% by own financing (EUR 59 112,09)

Project duration.

Planned project implementation period – 27 months

2. No. 2.1.1.4/1/25/I/010, “Improving the Energy Efficiency of the Administrative Building in Gulbene, Ābeļu iela 6”

Project description.

Improving energy efficiency simultaneously ensures a positive and favorable impact on the environment and ensures quality and appropriate conditions for the staff and clients of the Vidzeme District Court (in Gulbene) and the Gulbene Land Register Office, in the administrative building in Gulbene, Ābeļu iela 6.

Project objective.

Improving the energy efficiency of the building in Gulbene, Ābeļu iela 6, by carrying out energy certification of the building and construction works to increase energy efficiency, including implementing smart management solutions and improving infrastructure, in order to achieve primary energy savings for the building and promote progress toward zero-energy buildings.

Planned results.

  1. An energy certificate for the building has been prepared, with a report on economically justified energy-efficiency-improving measures.
  2. A building design has been prepared and approved by the building authority.
  3. Construction works – energy-efficiency-improving measures – have been carried out in accordance with the developed building design (under the supervision of a certified construction supervisor and a certified author’s supervisor).
  4. Primary energy savings relative to the total primary energy consumption before the start of the project – 53%.

Project costs.

The planned total eligible costs of the project – EUR 220 573,69

Sources of financing for the project’s planned eligible costs – 62,10 % of eligible costs is planned to be covered by European Regional Development Fund financing (EUR 136972,09), 10,96% by state budget financing (EUR 24 171,55), and 26,94% by own financing (EUR 59 430,05)

Project duration.

Planned project implementation period – 27 months

3. No. 2.1.1.4/1/25/I/011, “Improving the Energy Efficiency of the Administrative Building in Aizkraukle, Spīdolas iela 4”

Project description.

Improving energy efficiency simultaneously ensures a positive and favorable impact on the environment and ensures quality and appropriate conditions for the staff and clients of the Zemgale District Court (in Aizkraukle) and the Aizkraukle Land Register Office, in the administrative building in Aizkraukle, Spīdolas iela 4.

Project objective.

Improving the energy efficiency of the building in Aizkraukle, Spīdolas iela 4, by carrying out energy certification of the building and construction works to increase energy efficiency, including implementing smart management solutions and improving infrastructure, in order to achieve primary energy savings for the building and promote progress toward zero-energy buildings.

Planned results.

  1. An energy certificate for the building has been prepared, with a report on economically justified energy-efficiency-improving measures.
  2. A building design has been prepared and approved by the building authority.
  3. Construction works – energy-efficiency-improving measures – have been carried out in accordance with the developed building design (under the supervision of a certified construction supervisor and a certified author’s supervisor).
  4. Primary energy savings relative to the total primary energy consumption before the start of the project – 30,3%.

Project costs.

The planned total eligible costs of the project – EUR 255 202,50

Sources of financing for the project’s planned eligible costs – 72,78 % of eligible costs is planned to be covered by European Regional Development Fund financing (EUR 185 730,96), 12,84 % by state budget financing (EUR 32776,05), and 14,38% by own financing (EUR 36 695,49).

Project duration.

Planned project implementation period – 27 months