The state joint-stock company “Tiesu namu aģentūra” has begun implementing the project under Measure 4.2.1.2 “Promoting energy efficiency improvements in state buildings” of specific support objective 4.2.1 “Promoting energy efficiency improvements in state and residential buildings” of the “Growth and Employment” Operational Programme of the European Regional Development Fund (ERDF).
Improving the Energy Efficiency of the Administrative Building at Daugavgrīvas iela 58, Riga
Project description.
Improving energy efficiency simultaneously ensures a positive and favorable impact on the environment and quality, appropriate conditions for the staff and clients of the Kurzeme District Court of Riga.
Project objective.
To promote energy efficiency improvements in the state building and smart energy management and the use of renewable energy resources – at Daugavgrīvas iela 58, Riga.
Main project activities.
- Ensuring project management and preparing the project’s supporting documentation – administration specialists who will be financed under the project from the project applicant’s own funds;
- Energy certification, provided by an independent expert – the issuer of the building’s energy certificate;
- Development of the building design, provided by an independent designer selected through the procurement procedure, in accordance with the specified design work tasks;
- Project preparation documentation, provided by an independent expert selected through the procurement procedure.
- Construction supervision, provided by a certified construction supervisor selected through the procurement procedure.
- Author’s supervision, provided by a certified author’s supervisor selected through the procurement procedure.
- Carrying out construction works (incl. energy-efficiency-improving measures – insulating the attic floor, replacing existing wooden exterior doors, replacing the attic hatch, improving the building’s external enclosing structures, improving the building’s technical systems, replacing glass blocks with new windows/insulating window openings, insulating the above- and below-ground sections of the basement wall, insulating the 1st-floor floor/1m below ground level), provided by an independent contractor selected through the procurement procedure in accordance with the specified construction work tasks.
Planned results.
- An Energy Certificate for the Building has been prepared (with a report on economically justified energy-efficiency-improving measures);
- A building design has been prepared and approved by the building authority;
- Construction works – energy-efficiency-improving measures – have been carried out in accordance with the developed building design (under the supervision of a certified construction supervisor and a certified author’s supervisor).
The reduction in annual primary energy consumption, to be achieved by the end of 2020 / beginning of 2021 – 229.3186 MWh/year.
The calculated annual reduction in greenhouse gas emissions, to be achieved by the end of 2020 / beginning of 2021 – 46.1432 tonnes of CO2 equivalent per year.
Project duration.
Preparation of the project’s supporting documentation began in Q3 2017
Design works are planned to be carried out – 2018
Construction works are planned to be carried out – 2019-2020
Planned project start date – Q1 2019
Planned project implementation period – 22 months